Learn more about our new building project timeline and progress.
Watch our progress:
Sept 14, 2024, Setting up tent for Groundbreaking ServiceSept 14, 2024, Setting up tent for Groundbreaking ServiceSept 15, 2024 Groundbreaking ServiceSept 15, 2024 Groundbreaking ServiceSept 15, 2024, Groundbreaking ServiceJune 30, 2025, Steel deliveredAug 19, 2025, Excavation beginsAug 30, 2025, Moving dirtAug 31, 2025, Work on footingsAug 31, 2025, Bible verses on frost wallSept 8, 2025, Work on footingsSept 11, 2025 Fencing going inSept 18, 2025, Footings pit dugSept 22, 2025, Footings setSept 23, 2025, Elevator pit pouredSept 23, 2025, Footings pouredSept 24, 2025, Frost wall setSept 24, 2025, Elevator walls formedSept 27, 2025, Tar on frost wallsSept 28, 2025, Ready to backfil the frost wallOct 3, 2025, Underground plumbing in placeOct 8, 2025, Placing gravel for slabOct 9, 2025 Spot footings with anchor bolts in place for columnsOct 15, 2025 Ready to Pour the slabOct 23, 2025, Pouring the slabOct 23, 2025, Pouring the slabOct 23, 2025 Power Screed for perfect levelingOct 23, 2025 Slab poured & ready to finishOct 23, 2025, The slab being finishedOct 24, 2025, Slab completedOct 24, 2025, Slab completedOct 28, 2025 Slab & backfill ready for steel buildingDec 1, 2025 Steel Structure began todayDec 11, Beginning of the Steel StructureDec 22, Starting the 2nd half of the steel structureDec 22, The last major column setDec 24, 2025 More trusses installed. Dec 29, 2025 One more wallJan 2, 2026 Last steel wallJan 8, 2026 Window frames in placeJan 9, 2026 Steel Structure almost completedJan 19, 2026 Installing roof insulationJan 23, 2026 Wall siding beginsJan 31, 2026 South Wall with windows aboveFeb 13, 2026 Final WallFeb 17, 2026 Walls finishedFeb 19, 2026 Wainscot installedFeb 27, 2026 Exterior structure complete2026-02-27 Interior – no inside framing 12026-02-27 Interior – no inside framing 22026-02-27 Interior – no inside framing 3 Feb 27, 2026 Exterior Complete
Timelaspse video of the foundation and steel structure being erected March 16, 2026 Phase 4a- Purchase of Wall Insulation
Latest Update
2/16/2026- The contractor installing the steel structure started on December 1st to erect the building and is making good progress despite heavy winds and some snow. The exterior structure of the building is complete and next is interior wall insulation.
3/23/2026- Fundraising Update: We have completed the steel structure and our building is ‘dried in’. Fundraising for the interior wall insulation is complete (Thanks to God helping us with the Italian Breaking Bread FUN-raiser Meal. Insulation has been ordered and when it is here we will install it.
Next Milestone
Our next milestone will be when we get the interior wall insulation installed.
Phase 2 – Underground utilities, footings, and floor slab [completed & paid for with part of a loan]
Phase 3 – Building erection including insulation, doors & windows [completed except for wall insulation]
Phase 4 – Wall insulation, dying of the concrete as flooring, 2nd level & interior framing
Phase 5 – Vestibule (front entry doors), rough-in for plumbing, electric and heating & air conditioning, Connection Corridor, Interior sheetrock & finishes
Phase 6 – Parking, water, and septic system
Phase 7 – Media, furniture, kitchen and elevator
Next Funding Goal
We have completed phase 4a fundraising of roughly $22,075 to purchase the wall insulation. The insulation has been ordered so we can install it and then begin fundraising for interior framing materials.
Volunteers
To volunteer, please click the button below so we can understand your schedule and how to best make use of your unique skills.