Building Updates
Learn more about our new building project timeline and progress.
Watch our progress:























in place for columns
































Latest Update
2/16/2026- The contractor installing the steel structure started on December 1st to erect the building and is making good progress despite heavy winds and some snow. The exterior structure of the building is complete and next is interior wall insulation.
3/16/2026- Fundraising Update: We have completed the steel structure and our building is ‘dried in’. Our next fundraising goal is $22,075 for the interior wall insulation purchase that we will install when it has been ordered and delivered.
Next Milestone
Our next milestone will be when we get the interior wall insulation installed.
Current Phase of Construction
We are into “Phase 4a” of construction.
Phase 1 – Planning, engineering & steel building structure [completed & paid for]
Phase 2 – Underground utilities, footings, and floor slab [completed & paid for with part of a loan]
Phase 3 – Building erection including insulation, doors & windows [completed except for wall insulation]
Phase 4 – wall insulation, 2nd level & interior framing, and rough-in plumbing, electric & HVAC
Phase 5 – Vestibule (front entry doors), Connection Corridor, Interior sheetrock & finishes and kitchen
Phase 6 – Parking, water, and septic system
Phase 7 – Media, furniture and elevator
Next Funding Goal
To complete phase 4a we needed to raise roughly $22,075 to purchase the wall insulation. We have raised $1,776 (8%) of that amount to date. Once it has been raised we will order the insulation so we can install it and begin fundraising for interior framing materials.
Volunteers
At this point there is not much for volunteers to do but there will be soon. Keep watching and click the button below to put your information there so we can contact you when we’re ready.
To volunteer, please click the button below so we can understand your schedule and how to best make use of your unique skills.